5 tips for an efficient precast plant project

This post is also available in: Русский (Russian)

Are you planning to establish a precast concrete plant? But are you perhaps still a bit unsure how to proceed, what steps to take next, what points to pay attention to? If you are, in my experience many professionals have the same exact thoughts. So, as I and my colleagues at Elematic have been working with precast concrete plant projects for quite a while, we wish to share some of the key points with you.

1. Confirm location / space where the precast plant will be built

Firstly, it’s important to keep in mind that a standard precast plant can’t be built just anywhere. A plant consists of heavy-duty hardware that cannot be moved around easily – unless designed movable – and the actual production process also needs to happen in a certain order. Thus, when the plant layout is designed, the designer needs to know not only the amount of space but also its shape, exact measurements, ground conditions and the location of raw materials and existing / planned roads for element logistics.

Elematic delivered precast wall panel production plant at Karkas Monolit in Nizhny Novgorod, Russia.

2. Make sure that you share detailed product descriptions

Not only the place information but also product descriptions will be needed before the engineering project can start. Without them, the machinery and the plant layout may not be optimized for your production needs. The descriptions should tell what kind of precast elements – hollow-core, walls, piles, pillars – you will be producing, with their measurements and details, shapes, openings, recesses and ducts, and possibly insulation thicknesses or cross sections and lengths.

3. Set up a professional project team

Even if the plant supplier such as Elematic has a professional project organization and a dedicated project manager, you will also need your own project manager. The project manager should have extensive experience as they have a key role in the successful completion of the project. They handle the whole project, including communication and co-operation with the production line supplier and also with all other related parties. To keep the project in schedule and avoid mistakes in the implementation, a skilled team – engineers, mechanics, welders, electricians, etc. – with enough manpower is also a must-have. Do not forget to arrange proper tools and equipment, for example a tachymeter, to the site. Your project manager and at least some of the team members must have good command of the English language.

4. Make sure that the infrastructure for the production lines is on schedule

Precast production line installation cannot begin before the building and, in particular, its floor and ground structures are finished. Furthermore, before the test runs can start, the plant site will need to have a proper, continuous feed for electricity, water and compressed air. Waste water handling, sewerage and lighting in the  premises are also needed.

Precast products storage at Hanwha E&C precast plant in Iraq

5. Ensure that you have personnel and all raw materials available for commissioning

At the time of the factory start-up, you should have the plant personnel in place. This way they can learn in practice how to run the factory.  We also highly recommend to take separate machine and plant training courses. They will greatly help the personnel in their daily routines and make sure that minor mistakes do not stop the whole production later on. In addition to the personnel, you will also need to have all raw materials for the concrete mix available. Otherwise it will be impossible to make any proper test runs nor start the actual production.

Of course, if you work with us, we will go through all these points with you and make sure that your project proceeds on time and in a professional manner. But I hope this helps you in pre-planning the project on your side – together we will make your project a success and get your precast plant running as smooth and as fast as possible!

Ari Syrjä, Project Manager at Elematic

Ari Syrjä, Project Manager

Elematic Oyj

Read more about precast plant projects:

Would you like to set up a precast plant, but aren’t quite sure of the schedule? Are you uncertain of which aspects affect the project and how much time should be reserved for each step?

Demands for well-functioning project management have increased over the past few years. This is where the pressure to shorten delivery times and the ability to deliver a tight project cycle meet years of know-how. Elematic’s streamlined project services attend to the varying precasting needs on every continent – from the preliminary phase to start-up and commissioning.

Bismayah New City is a visionary dream rapidly becoming reality in Iraq thanks to the drive of Korean contractor Hanwha and the world’s biggest precast concrete plant, supplied by Elematic.

Subscribe to Blog via Email

Enter your email address to subscribe to this blog and receive notifications of new posts by email.

Would you like to know more about the steps of establishing a precast concrete factory? Contact us!

 

2 Comments Add yours

  1. bageshree says:

    Thank you for sharing this information with us about tips for efficient precast plant project. We uses the services of Teracaste, they are are suppliers of Precast Concrete Products to Builders, Contractors, Architects& Landscape Consultants. visit them for more info http://www.terracast.in/

Leave a Reply